Construction Schedule for the Week of November 7, 2022
The lights are on and functioning for both runways and taxiways. During the week of November 7, crews will be cleaning up and finishing minor tasks, which will be outside the runway and will not impact aircraft operations.
Delivery of the PAPIs for 01, 08 and 19 has been delayed until March 2023. Unfortunately, the airport will be without PAPIs until they are delivered and installed. The VASIs on Runway 26 will continue to be on and the MALS on the end of Runway 19 have been on since November 4.
Additionally, delivery of the emergency generator is delayed until June 2023. Upon installation of the generator, runway lights will function during power outages.
Thank you again for your continued patience throughout this project. Enjoy the new lights!
How do I stay informed?
Click here to send an email to the project group.
Sign up for our eNews and select Aviation, we will be sending out regular emails with the construction updates and schedule.
Notices of the project construction will include signage at the airport, direct mailings, newspaper advertisements and flyers at the airport.
If you have any questions concerning this project, please contact the project email or call the port at 509-375-3060
Monday – Thursday:
7 AM – 4:30 PM
Friday:
8 AM – Noon