September 20, 2024
Crews worked throughout the week on the pavement maintenance of both runways at Richland Airport.
Runway 1-19 was reopened Friday, September 20.
Work will resume on Runway 8-26 on Monday, September 23.
Crews were able to complete the work around the front of the fuel island while the runways were shut down, which was not planned until later in the project.
View the construction schedule here.
Monday – Thursday:
7 AM – 4:30 PM
Friday:
8 AM – Noon