Richland Airport Pavement Maintenance Update – Oct. 4, 2024

October 4, 2024

To date, both runways, alpha-delta taxiways and the south and main ramps have had crack repair performed. Fog seal has been laid down.

Next week, work will focus on the north hangar area (highlighted in cyan on the map).
Additional crack repair will be performed, followed by seal coat and striping.
There will be a period of time when access to hangars will be restricted in order to perform the necessary maintenance.

Contact

Summers Miya
Public Information Officer

Closed, but still awesome.

  • 1st day of January (New Year’s Day)
  • 3rd Monday of January (Martin Luther King Day)
  • 3rd Monday of February (President’s Day)
  • Last Monday of May (Memorial Day)
  • 19th day of June (Juneteenth)
  • 4th day of July (Independence Day)
  • 1st Monday in September (Labor Day)
  • 11th day of November (Veteran’s Day)
  • 4th Thursday in November (Thanksgiving Day)
  • The day immediately following Thanksgiving Day
  • 25th day of December (Christmas Day)