Richland Airport Apron Improvement Project Update – September 21, 2026
September 21, 2026
Crews completed compaction of the base rock and placed the first lift of asphalt last week. Concrete placement for the tie-down anchors is scheduled for later this week. The contractor tentatively plans to perform the striping work in front of the fuel facility next week, which will require a temporary shutdown of the 100LL self-service fuel system for several days. Once we confirm a firm schedule, we will send a notification and issue a NOTAM.