Richland Airport Apron Improvement Project Update – August 28, 2026
August 28, 2026
This week, the contractor made great progress milling and removing the areas of thin asphalt, as well as the tie-down anchors that will be relocated. Excavation has taken place and compaction testing has begun in those areas. Next week, the contractor will begin laying and compacting the sub-base and base rock. The project is on schedule.