May 15, 2026

Crews made considerable progress this week on the Prosser Airport project. Lots of electrical details were sorted out, including setting all the base cans for the runway lights and pouring the foundations for the taxiway signs and PAPIs.

Taxiway A had a significant amount of wide (48″) crack repair that runs laterally across a dozen or so locations. The new asphalt that was laid wasn’t perfectly flat, so we’ve been working with the contractor to remedy it. We think we have a path forward and don’t expect it to significantly delay the project.

Thank you for your patience and cooperation.

Contact

Summers Miya
Marketing & Communications Manager

Closed, but still awesome.

  • 1st day of January (New Year’s Day)
  • 3rd Monday of January (Martin Luther King Day)
  • 3rd Monday of February (President’s Day)
  • Last Monday of May (Memorial Day)
  • 19th day of June (Juneteenth)
  • 4th day of July (Independence Day)
  • 1st Monday in September (Labor Day)
  • 11th day of November (Veteran’s Day)
  • 4th Thursday in November (Thanksgiving Day)
  • The day immediately following Thanksgiving Day
  • 25th day of December (Christmas Day)