2501 Stevens Drive Project

Project Overview

The 2501 Stevens Drive Project is a key phase of the Port of Benton’s broader effort to modernize its industrial property in North Richland. The project includes the construction of a new, approximately 12,000-square-foot facility featuring modern office space and six approximately 1,000-square-foot flex bays, with the ability to add four additional bays in the future. The facility will accommodate the relocation of Barnhart Crane’s existing office operations, supporting the company’s continued growth and enabling the future removal of aging office space at 2579 Stevens Drive as part of efforts to meet Washington’s clean building requirements.

Supported by an approximately $5.4 million funding package from the Community Economic Revitalization Board, Benton County Rural County Capital Funds, and the Port of Benton, the project will improve operational efficiency, support tenant retention, and create space for future industrial users. Architects West is advancing the design toward permit-ready status, targeted for early 2027, with construction and tenant relocation planned for mid-2028. As a cornerstone of future intermodal expansion, the project increases the site’s industrial development capacity and positions the property for long-term economic growth, private investment, and job creation.

News & Updates

Sign up to receive Port news and updates in your inbox.

Highlights

  • New building concept totaling approximately 12,000 square feet.
  • Includes modern office space, and six approximately 1,000-square-foot flex bays.
  • Designed with the ability to expand by four additional flex bays in the future.
  • Supports relocation and removal of the existing office structure at 2579 Stevens Drive to comply with the Washington Clean Building Act 2019.

Budget and Funding

$2.4 million – Community Economic Revitalization Board (CERB) Loan

$1.7 million – Benton County Rural County Capital Funds

$1.3 million – Port of Benton Investment

Total Funding Package – Approximately $5.4 million (including a new building at this location)

Key Milestones

  • Architects West selected as project designer.
  • CERB funding secured and project contract executed.
  • Design advancing toward permit-ready status.
  • Commitment with Barnhart Crane to support their future growth.

Proposed Schedule

Early 2027

Target completion of permit-ready design

Early 2027

Permitting, bidding, and procurement

Mid 2028

Building construction and tenant relocation

Future Phases

Demolition of existing office space and continued modernization of the 2579 facility

Community and Economic Development Benefits

  • Cornerstone project for Future Intermodal expansion
  • Supports existing tenants while creating space for future industrial users
  • Improves operational efficiency and building code compliance
  • Increases industrial development capacity at the site
  • Positions the property for long-term economic growth, private investment, and job creation

Closed, but still awesome.

  • 1st day of January (New Year’s Day)
  • 3rd Monday of January (Martin Luther King Day)
  • 3rd Monday of February (President’s Day)
  • Last Monday of May (Memorial Day)
  • 19th day of June (Juneteenth)
  • 4th day of July (Independence Day)
  • 1st Monday in September (Labor Day)
  • 11th day of November (Veteran’s Day)
  • 4th Thursday in November (Thanksgiving Day)
  • The day immediately following Thanksgiving Day
  • 25th day of December (Christmas Day)