Weekly Update: Richland Airport (RLD) Electrical Replacement Project – Week of September 6, 2022

Weekly Construction Update – As part of the Richland Airport Electrical Replacement Project, the port will be issuing these weekly construction updates to keep airport users as well informed as possible in our attempt to limit the impact on users. 

Construction Schedule for the Week of September 6, 2022
  • Runway 8-26 runway closure
  • Runway 1-19 shortened to 2,065 feet with displaced threshold south of Runway 8-26

     

Tuesday, September 6 at 6 a.m., the electrical contractor will be moving into the intersection of the runways. Over the next two weeks, Runway 1-19 will be shortened to 2,065 feet with a displaced threshold south of the runway’s intersection. Runway 8-26 will be completely closed. The runways will be open over the weekend of September 10-11.

The contractor will be focusing on all electrical work within the intersection. On Tuesday, September 6 at 6 a.m., the contractor will reduce Runway 1-19 to 2,065 feet south of the runway intersection and will then close Runway 8-26. The shortened runway 1-19 will not have lights or navigation aids. During this period of time, Taxiway A, south of Taxiway B, and Taxiway B east of Runway 1-19, will be open. This will allow an additional run-up area on Runway 1-19 north of the displaced threshold.

There will be a lot of construction activity during this two-week period. Please be very cautious and aware of the contractor’s activity. Additionally, please be aware and cautious of the low-profile barricades in the vicinity of the reduced Runway 1-19. During the closure, regular radio calls will be made when any aircraft Runway 1-19 as their destination.  Please make the effort to notify pilots that you know may not be familiar with the construction project. 

The week of September 19-23, Runway 8-26 will be fully open, but will not have lights until Friday, September 23.

How do I stay informed?

Visit the Project website.

Click here to send an email to the project group.

Sign up for our eNews and select Aviation, we will be sending out regular emails with the construction updates and schedule.

Notices of the project construction will include signage at the airport, direct mailings, newspaper advertisements and flyers at the airport.

If you have any questions concerning this project, please contact the project email or call the port at 509-375-3060.

 

Project Contact

Closed, but still awesome.

  • 1st day of January (New Year’s Day)
  • 3rd Monday of January (Martin Luther King Day)
  • 3rd Monday of February (President’s Day)
  • Last Monday of May (Memorial Day)
  • 19th day of June (Juneteenth)
  • 4th day of July (Independence Day)
  • 1st Monday in September (Labor Day)
  • 11th day of November (Veteran’s Day)
  • 4th Thursday in November (Thanksgiving Day)
  • The day immediately following Thanksgiving Day
  • 25th day of December (Christmas Day)