October 30, 2024
Weather permitting, we will shut down both runways, 8/26 and 1/19, next Tuesday, November 5, to apply the final coat of paint and add a phosphorescent bead that increases nighttime reflectivity. 1/19 will continue to be shut down on Wednesday, November 6, and ramp work will continue through Thursday.
Thank you very much for everyone’s flexibility throughout the project. We are excited to push through to the finish line!
Watch NOTAMs in case the weather changes the schedule.
Monday – Thursday:
7 AM – 4:30 PM
Friday:
8 AM – Noon