May 8, 2026
Crews got off to a quick start this week on the Prosser Airport Pavement & Lighting Replacement Project.
Most of the wide crack areas have been excavated, compacted, and prepped for asphalt.
Over 4000’ of conduit has been run for the electrical wire, and several of the concrete pads for lights have been poured.
Thank you for your patience and cooperation.