Richland Airport Apron Improvement Project Update – September 4, 2026

September 4, 2026

Crews remain on schedule. This week focused on placing the large base rock, compacting it, and bringing it to the correct grade. Next week, crews will lay and compact a finer layer of crushed rock. We could see paving crews out as soon as next Friday to start laying asphalt.

 