Search
Close this search box.

Project Update: State Route 240 Rail Crossing

August 20, 2024

RICHLAND, Wash. – Port of Benton anticipated replacing the State Route 240 rail crossing this summer. However, while the construction drawings and specifications are complete, the Port still awaits approval from our government partners to advertise for construction bids. 

This approval is mandatory for receiving the federal funds to help pay for this project. 

The Port team is committed to completing this project as soon as possible. We will continue coordinating with our grant partners and expect to have an update soon. Unfortunately, we have no control over the delay. 

Project Funding

Port of Benton is paying for the $1.3 million SR 240 rail crossing replacement with an $865,000 National Highway Freight Program grant via the Washington State Department of Transportation and $435,000 in Port matching funds.

Planned Work

  • Replace the existing railroad crossing and the crossing’s flashing lights and gates where SR 240 crosses the Port’s railroad track
  • Port of Benton will continue asphalt and concrete maintenance on this crossing until it is replaced

The Port will share updates and the resulting construction schedule as soon as they are available to keep you informed.

Contact

Summers Miya
Public Information Officer

Closed, but still awesome.

  • 1st day of January (New Year’s Day)
  • 3rd Monday of January (Martin Luther King Day)
  • 3rd Monday of February (President’s Day)
  • Last Monday of May (Memorial Day)
  • 19th day of June (Juneteenth)
  • 4th day of July (Independence Day)
  • 1st Monday in September (Labor Day)
  • 11th day of November (Veteran’s Day)
  • 4th Thursday in November (Thanksgiving Day)
  • The day immediately following Thanksgiving Day
  • 25th day of December (Christmas Day)