Weekly Update: Richland Airport (RLD) Electrical Replacement Project – Weeks of October 28 – November 4, 2022

Weekly Construction Update – As part of the Richland Airport Electrical Replacement Project, the port will be issuing these weekly construction updates to keep airport users as well informed as possible in our attempt to limit the impact on users. 

Construction Schedule for the Weeks of October 28 – November 4, 2022
The project is almost done! 
By November 4, the lights should be on for both Runways and Taxiways!

For this week, Runway 1-19 and Taxiway A will remain closed from Monday morning at 6 a.m. until Friday afternoon at 4 p.m. Aircraft are still required to taxi from the main Apron via Taxilane D and across the north Apron to Taxiway B.
See attached exhibit map.

On Monday, October 31, a vault in the middle of the main apron, in front of Sundance Aviation will be replaced. Please be cautious when taxiing in this area, as there will be equipment and personnel working.

Late in the week, crews will need to make the last wire pull from the tower to the intersection of the runways. This is through existing conduit and vaults, however, there will be workers adjacent to these vaults for periods of time. No vehicles should be blocking the taxilanes and personnel will move out of the way of any active aircraft.

As a reminder, there will be no navigational lights, PAPIs, or approach lighting until the entire project is completed, other than the VASIs on Runway 26, which are currently operational. The new PAPIs have not yet been received, so there is not yet an anticipated installation date. 

Thank you for your continued patience throughout this project.

How do I stay informed?

Visit the Project website.

Click here to send an email to the project group.

Sign up for our eNews and select Aviation, we will be sending out regular emails with the construction updates and schedule.

Notices of the project construction will include signage at the airport, direct mailings, newspaper advertisements and flyers at the airport.

If you have any questions concerning this project, please contact the project email or call the port at 509-375-3060

 

Project Contact

Closed, but still awesome.

  • 1st day of January (New Year’s Day)
  • 3rd Monday of January (Martin Luther King Day)
  • 3rd Monday of February (President’s Day)
  • Last Monday of May (Memorial Day)
  • 19th day of June (Juneteenth)
  • 4th day of July (Independence Day)
  • 1st Monday in September (Labor Day)
  • 11th day of November (Veteran’s Day)
  • 4th Thursday in November (Thanksgiving Day)
  • The day immediately following Thanksgiving Day
  • 25th day of December (Christmas Day)