May 29, 2026
The runway and taxiway are currently open. However, some work remains on the lighting system, and it will remain NOTAM’d out until next week.
The remaining slurry seal is scheduled for application on Monday, June 1. Areas receiving slurry seal will be closed to vehicular traffic for approximately 24 hours. Please plan accordingly if work activities are occurring near your hangar.
Crews are also expected to return in approximately one month to apply the second and third layers of runway striping. This work will require a brief additional closure, and more details will be provided in advance.
We appreciate your patience and cooperation as these final project elements are completed.
Contact
Summers Miya Marketing & Communications Manager

|